Finalize the quality control checklist for the first 20 units. serena south
Serena South remains on track for its projected completion date of March 2027. The project continues to be a cornerstone of the Serena brand's expansion, maintaining high standards of architectural excellence and investor ROI.
65% Complete. Structural framing for the primary villa blocks is finished; interior finishing is currently underway. Phase 3 (Landscaping): Scheduled to commence Q3 2026. 4. Market Performance & Sales Data relating to Serena Hotels (TPS Eastern Africa)
Launch the "Life in the South" digital campaign to move remaining inventory.
Average unit value has seen an 8% uptick since the groundbreaking ceremony due to high demand in the southern corridor. 5. Strategic Objectives for Q3-Q4 Serena South remains on track for its projected
75% of units are currently under contract or reserved.